How Long Does It Take to Build a Website?
Steve Burk Co-Founder 7 min read
A website for a service business typically takes 3 to 10 weeks to build. A 5 to 8 page brochure site takes roughly 3 to 6 weeks. A 15 to 30 page site with service and location pages takes roughly 6 to 10 weeks. Sites with booking, ordering or a client portal take longer, often 10 to 16 weeks.
If one agency quoted you 2 weeks and another quoted 4 months, both may be telling the truth. The build itself is rarely the slow part. Waiting is. Waiting on copy, on photos, on sign-off from a partner who missed the first meeting. Below is where the time goes and how we keep a build on track. It is the same approach behind our website design services.
How Long Does It Take to Build a Website? Timelines by Type
Site size sets the floor. More pages mean more copy to write, approve and test.
Brochure Site, 5 to 8 Pages: Roughly 3 to 6 Weeks
Home, about, services, reviews and a contact page. This is the right site for a business that mostly needs to look credible when a referral looks it up. The 3-week end assumes your copy and photos are ready on day 1.
Service and Location Site, 15 to 30 Pages: Roughly 6 to 10 Weeks
This is where most growing service businesses land. Each service gets its own page, and each town you serve may get one too, because those pages rank and give ad clicks a place to land.
Sites With Booking, Ordering or a Portal: Often 10 to 16 Weeks
Booking, ordering, quote calculators and client portals all connect to another system. Each connection has to be set up and tested with real data. Plan on the long end if that system is old or poorly documented. We go deeper on this in our website redesign checklist.
The Website Development Timeline, Phase by Phase
Every build moves through the same 6 phases. The ranges below fit a typical 15 to 30 page service site. A brochure site sits at the short end of each, and some phases overlap.
- Discovery and content, 1 to 2 weeks: goals, pages and approvers are agreed, and copy and photos start coming in.
- Design, 1 to 2 weeks: the home page and 1 or 2 key page templates are designed and revised.
- Build, 1 to 3 weeks: the approved design becomes working pages, forms and integrations on a private staging link.
- Content load, 2 days to 1 week: final copy, photos and page titles go into every page.
- QA and tracking, 3 days to 1 week: every page is checked on a phone and every form and conversion is tested.
- Launch, 1 day plus 2 weeks of watching: the domain switches over, redirects go live and the first real leads are checked by hand.
Launch day is not the finish line. The first 2 weeks surface things no test catches, and after that the site needs updates, backups and small edits for as long as it runs. This ties directly into what to budget for website maintenance, which we cover in a separate post.
What Actually Sets How Long a Website Takes to Build
Sites with the same page count can finish 2 months apart. In our experience, 3 things decide it, and only 1 of them is technical.
How Fast Content and Approvals Come Back
Every phase ends with a sign-off. If feedback takes 2 days, the project moves. If it takes 2 weeks, each phase stretches by 2 weeks, and a build with 4 sign-offs can lose 2 months without anyone noticing.
How Much Copy Already Exists
Owners often plan to write the copy themselves over a weekend. That weekend rarely comes. A site with 20 service and location pages needs 20 pages of specific writing, usually the longest single task in the project. If copy exists and only needs editing, weeks come off the timeline.
Integrations
A contact form that emails you is simple. A form that creates a CRM record, tags the lead source and sends a text back is 3 systems that have to agree. Booking tools, payment processors and portals each add their own setup and testing, often a week or more apiece.
Take a construction company. The project photos that sell the work are scattered across crew phones. Each trade needs its own service page. The estimate request has to reach the right person with the job address, scope and budget attached. None of that is hard, but all 3 timeline drivers show up at once. The same problem looks different by vertical, as our page on web design for construction companies shows.
What Should Never Be Rushed Before a Website Launch
When a launch date slips, the pressure lands on the last phase. That is the phase that decides whether the site produces leads you can count. These 3 items get checked in full, even if launch moves by a few days.
- Tracking has to be tested with real submissions, because a conversion that fires twice or not at all misleads every ad decision after it.
- Every form has to be tested all the way to the inbox, since a form can show a thank-you message while the email goes to spam or to an address nobody checks.
- Every old URL needs a redirect to its closest new page, or the rankings the old site earned over years can disappear in weeks.
Fixing any of these after launch costs more than doing it before. You lose the leads in between, and you usually cannot get that data back.
A launch checklist turns those 3 items into tests someone signs off on. At a minimum, it should confirm each of these:
- Every form was submitted on a phone and a desktop, and each one arrived in the right inbox and CRM.
- Analytics and ad conversions each recorded the test lead exactly once.
- Every old URL redirects straight to the right new page.
- No page is still blocked from search, and the sitemap is submitted to Google Search Console.
- The domain, hosting and every account are in the owner's name.
Run the checklist before launch and again 2 weeks after. The second pass catches what changed once real visitors arrived.
Not sure whether your current site is tracking its leads correctly? Find out in a few minutes. Take the free Growth Score →
How to Keep a 6-Week Website Build From Taking 6 Months
Sites rarely stall in the build. They stall in the gaps between phases. These habits keep a project on its original date:
- Name 1 decision-maker who can approve design and copy without a committee.
- Set a content deadline before design starts, and move the launch date if it is missed instead of cutting QA short.
- Agree in writing on 2 rounds of revisions per phase, so feedback arrives complete instead of in pieces.
- Park new ideas for a second phase instead of adding pages mid-build.
The last one matters most. Scope creep is how most 6-week sites turn into 6-month sites. A site that launches with 20 good pages and adds 5 more next month beats a site that waits for all 25.
What a Well-Run Website Rebuild Produces
A fast timeline only matters if the site performs after launch. One client saw 2.60x ROAS and $17,204 booked from organic search.
That client is Just Better Moving, a mover in Parsippany. We rebuilt its website and its Google Ads account. Over 16 weeks, the ads returned 2.60x on spend and produced 27 booked moves. Over the same 16 weeks, the site booked 23 more moves worth $17,204 from organic search. You cannot know either number with a form that sends leads to spam or tracking that fires twice.
So plan on 3 to 6 weeks for a small site and 6 to 10 for a service and location site, then protect those dates by getting content ready early. Every month a finished site waits on approvals, the old site keeps turning visitors away. We have seen this play out firsthand, as our post on what your website costs you every month explains.
Is your website leaking the leads your marketing earns? Talk to our web design team about a site built to convert.
Frequently Asked Questions
Can a website be built in a week?
A simple 1 to 3 page site on a template can go live in a week if the copy, photos and logo are ready on day 1. A custom site for a service business rarely can. The time goes into writing, approvals and testing every form and tracking tag, which are the parts that decide whether the site brings in leads.
How long does a website redesign take compared to a new build?
A redesign usually takes about as long as a new build of the same size, and sometimes longer. You still need copy, design, build and testing, plus a redirect for every old URL and a check that the pages that ranked keep their content. Most service business redesigns land in the 6 to 10 week range.
What slows down a website project the most?
In our experience, waiting on content and approvals causes more delay than design or development. A site cannot be built around copy that does not exist, and each week a sign-off sits unanswered adds a week to launch. Naming 1 decision-maker and setting a content deadline before design starts prevents most of it.